| What is a PD&E Study?
A brief explanation of
the PD&E Study process is provided below. The PD&E process was developed to ensure that transportation
projects are developed with consideration of current
engineering standards, project costs and minimization of
social and environmental impacts, while involving the public
throughout the entire study process. The basic activities of
a PD&E study include:
Data Collection
The first major work effort is the collection of all
available data pertaining to the study corridor including
existing roadway characteristics, traffic counts, existing
and future land uses, drainage patterns, locations of
wetlands and habitat for threatened or endangered species,
potential contamination sites, etc.
Alternatives
Development and Analysis
Once the data collection is complete and the needs of the
corridor have been determined, various improvement
alternatives will be developed. For a trail project, these
alternatives include the alignments, street crossings, trail
heads and trail amenities. The environmental impacts, social
impacts and costs of these alternatives will be quantified
and summarized in a comparative matrix.
Public
Information Workshops
To ensure the public is well informed, two public
information workshops were scheduled for the project. Because
of the large project area, three meeting locations were
provided for each workshop. The same information was
presented at each meeting location. With input received at
the workshops, the project team finalized the preferred alternative(s).
Final Acceptance
After the comments from the public workshop have been
addressed, the project reports are finalized and submitted
to Volusia County, Brevard County, and FDOT for location and
design concept acceptance. Once this acceptance is received,
the study phase of the project will be complete. The phases
that would follow the study phase include the design of the
approved improvements, possible right-of-way acquisition and
construction of the improvements. |